Wastewater

VILLAGE OF MT. CORY

COLLECTION SYSTEM, PUMP STATION, AND FORCE MAIN

Final construction completed. System provides sanitary sewer service to 105 homes within the Village. Wastewater is being be pumped to a controlled discharge lagoon at the Village of Rawson.

PRELIMINARY ENGINEERING REPORT

Prepared in accordance with USDA, Rural Development guidelines, to evaluate collection and treatment alternatives.

VILLAGE OF BENTON RIDGE

COLLECTION SYSTEM, PUMP STATION, AND FORCE MAIN

Final design is currently in progress. System will provide sanitary sewer service to 130 homes within the Village. Wastewater will be pumped to a controlled discharge lagoon at the Village of Rawson.

PRELIMINARY ENGINEERING REPORT

Prepared in accordance with USDA, Rural Development guidelines, to evaluate collection and treatment alternatives.

VILLAGE OF MT. BLANCHARD

PRELIMINARY ENGINEERING REPORT

Currently in progress.

GENERAL PLAN FOR WASTEWATER

Evaluation of several sewage collection and treatment alternatives including construction and operation/maintenance cost comparisons and recommendations to satisfy OhioEPA - Findings and Orders.

VILLAGE OF JENERA

PRELIMINARY ENGINEERING REPORT

Currently in progress.

GENERAL PLAN FOR WASTEWATER

Evaluation of several sewage collection and treatment alternatives including construction and operation/maintenance cost comparisons and recommendations to satisfy OhioEPA - Findings and Orders.

VILLAGE OF ARLINGTON

LIFT STATION IMPROVEMENTS

Preparation of specifications for equipment replacement/upgrades at the Village's main sanitary sewer pumping station.

INFLOW/INFILTRATION STUDY

Manhole inspection, smoke testing, flow monitoring, and internal inspection of sanitary sewer system.

LIBERTY BENTON LOCAL SCHOOL DISTRICT

Preparation of plans and specifications for sanitary sewer pump station and force main to connect the middle school to the City of Findlay sewer system.

SYCAMORE SPRINGS GOLF CLUB

Preparation of plans for an extended aeration wastewater treatment plant.

ANNANDALE BUSINESS COMPLEX - OTTAWA, OHIO

Development included preliminary surveying and plan preparation, Village and Ohio EPA approval of 470 LF of gravity 8" sanitary sewers serving three large commercial lots. Also included sanitary lift station and 550 LF of directional drilled 4" sanitary force main to the Village of Ottawa.

BROOKHAVEN SUBDIVISION - OTTAWA, OHIO

Project included 2,500 LF of gravity sanitary sewers serving 35 lots in a residential subdivision, a sanitary lift station, and a 4" force main to existing Village of Ottawa facilities. A section of the force main was bored and jacked under U.S. Route No. 224.

SAGER ADDITIONS, PHASE III - GLANDORF, OHIO

Project included 1,500 LF of gravity sanitary sewers serving 20 lots.

 

 